National: R-410A VRF systems built from pre-2026 components must be installed before Jan 1, 2027
The rule: under EPA's Technology Transitions rule, 40 CFR 84.54(c)(2), new residential and light commercial VRF systems using a refrigerant with a GWP of 700 or greater, which includes R-410A, have been restricted since Jan 1, 2026. The rule still lets such a system be installed before Jan 1, 2027 if all of its specified components were manufactured or imported before Jan 1, 2026.
Why it matters now: counting from Monday, Nov 9, about seven weeks of install time are left for R-410A VRF jobs built from pre-2026 stock, and the Thanksgiving and Christmas weeks eat into that. A separate, narrower path runs to Jan 1, 2028 only where an approved building permit issued before Oct 5, 2023 specifies the refrigerant.
For the office: if an R-410A VRF job is still on the board, confirm the manufacture or import dates of every specified component and lock in the install date before Thanksgiving week. Johnstone's Mitsubishi training in Jacksonville on Nov 12 is one local option if your crews are moving to newer equipment.